NEW QUESTION 1
A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

  • A. Plan Stakeholder Management
  • B. Identify Stakeholders
  • C. Manage Stakeholder Engagement
  • D. Control Stakeholder Engagement

Answer: A

NEW QUESTION 2
The Perform Integrated Change Control process occurs in which Process Group?

  • A. Initiating
  • B. Executing
  • C. Monitoring and Controlling
  • D. Planning

Answer: C

NEW QUESTION 3
Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

  • A. Project team
  • B. Focus group
  • C. Change control board
  • D. Project stakeholders

Answer: C

NEW QUESTION 4
Which is one of the determining factors used to calculate CPI?

  • A. EV
  • B. SPI
  • C. PV
  • D. ETC

Answer: A

NEW QUESTION 5
Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

  • A. Scope baseline
  • B. Scope management plan
  • C. Change management plan
  • D. Cost baseline

Answer: A

NEW QUESTION 6
One of the objectives of a quality audit is to:

  • A. highlight the need for root cause analysis.
  • B. share the process documentation among stakeholders.
  • C. offer assistance with non-value-added activities.
  • D. identify all of the gaps or shortcoming

Answer: D

NEW QUESTION 7
Outputs of the Control Communications process include:

  • A. expert judgment and change requests
  • B. work performance information and change requests
  • C. project management plan updates and work performance information
  • D. issue logs and organizational process assets updates

Answer: B

NEW QUESTION 8
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:

  • A. Cost management plan.
  • B. Work performance information.
  • C. Quality management plan.
  • D. Work breakdown structur

Answer: A

NEW QUESTION 9
When sequencing activities, what does the common acronym FF stand for?

  • A. Fixed Fee
  • B. Free Float
  • C. Fixed Finish
  • D. Finish-to-Finish

Answer: D

NEW QUESTION 10
An issue log is an input to which Project Human Resource Management process?

  • A. Manage Project Team
  • B. Acquire Project Team
  • C. Plan Human Resource Management
  • D. Develop Project Team

Answer: A

NEW QUESTION 11
The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:

  • A. Define Activities.
  • B. Sequence Activities.
  • C. Define Scope.
  • D. Control Schedule.

Answer: A

NEW QUESTION 12
Which process involves developing an approximation of the monetary resources needed to complete project activities?

  • A. Estimate Costs
  • B. Control Costs
  • C. Determine Budget
  • D. Plan Cost Management

Answer: A

NEW QUESTION 13
Which of the following are three inputs to the risk register?

  • A. Risk register updates, stakeholder register, and quality management plan
  • B. Communication management plan, enterprise environmental factors, and activity duration estimates
  • C. Risk management plan, activity cost estimates, and project documents
  • D. Project scope statement, organizational process assets, and scope baseline

Answer: C

NEW QUESTION 14
Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?

  • A. Define Activities
  • B. Direct and Manage Project Work
  • C. Develop Project Management Plan
  • D. Develop Project Charter

Answer: D

NEW QUESTION 15
Projects are separated into phases or subprojects; these phases include:

  • A. feasibility study, concept development, design, and prototype.
  • B. initiate, plan, execute, and monitor.
  • C. Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance.
  • D. Identify Stakeholders, develop concept, build, and tes

Answer: A

NEW QUESTION 16
Projects are undertaken by an organization to support the:

  • A. Product performance.
  • B. Budget process.
  • C. Collective capabilities.
  • D. Organizational strateg

Answer: D

NEW QUESTION 17
Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?

  • A. Histograms
  • B. Scatter diagrams
  • C. Flowcharts
  • D. Checksheets

Answer: D

NEW QUESTION 18
What type of project structure is a hierarchically organized depiction of the resources by type?

  • A. Organizational breakdown structure (OBS)
  • B. Resource breakdown structure (RBS)
  • C. Work breakdown structure (WBS)
  • D. Project breakdown structure (PBS)

Answer: B