Master the PMI-ACP PMI Agile Certified Practitioner (PMI-ACP)® content and be ready for exam day success quickly with this Passleader PMI-ACP exam cram. We guarantee it!We make it a reality and give you real PMI-ACP questions in our PMI PMI-ACP braindumps.Latest 100% VALID PMI PMI-ACP Exam Questions Dumps at below page. You can use our PMI PMI-ACP braindumps and pass your exam.

Also have PMI-ACP free dumps questions for you:

NEW QUESTION 1
Estimating costs for an Agile project starts with which of the following types of meetings?

  • A. Project Retrospective
  • B. Steering Committee
  • C. Release Planning
  • D. Sprint Planning

Answer: C

NEW QUESTION 2
The primary purpose of a Sprint retrospective is for the team to:

  • A. Review stories planned for the next sprint and provide estimates,
  • B. Demonstrate completed user stories to the Product Owner.
  • C. Discuss what went well, what didn't, and ways to improve.
  • D. Individually provide status updates on user stories in progress.

Answer: C

NEW QUESTION 3
Which term best describes an Agile project's approach to risk analysis?

  • A. Regression
  • B. Pareto
  • C. Qualitative
  • D. Monte Carlo

Answer: D

NEW QUESTION 4
Which layer of the product planning structure defines details at the capability or feature level?

  • A. Iteration
  • B. Roadmap
  • C. Release
  • D. Wave

Answer: C

NEW QUESTION 5
When developing user stories, user expectations are best captured in what form?

  • A. Acceptance tests
  • B. Entrance criteria
  • C. Done criteria
  • D. Go and no-go limits

Answer: A

NEW QUESTION 6
A business analyst has identified a new risk in an Agile project. What is the best first step the business analyst should take regarding this risk?

  • A. Call a meeting with the project manager and senior management to determine how the risk will be managed.
  • B. Email the project manager and add it to the risk register so that it is discussed during thenext daily standup.
  • C. Add the risk in a clearly visible location and ensure it is discussed after the next daily stand up.
  • D. Call an immediate meeting with all team members to discuss the newly identified risk.

Answer: C

NEW QUESTION 7
Applying the Pareto rule when prioritizing the Product Backlog means that:

  • A. features that are lower priority are more likely to slip to the next iteration.
  • B. the value of a feature is not realized until the feature is complete.
  • C. more recent requests are usually more important to the business.
  • D. a small percentage of the work will provide a large percentage of the value.

Answer: D

NEW QUESTION 8
For a critical project, a new team has been formed from various departments. The project manager should start team building by:

  • A. Creating a project charter, documenting roles and responsibilities of each member, and sending it to the team members.
  • B. Taking the team offsite for icebreaker sessions and other activities to ensure team members get to know each other.
  • C. Assembling the team and discussing roles and responsibilities of each member on the team.
  • D. Assembling the team and asking the members to achieve a milestone in a small iteration.

Answer: C

NEW QUESTION 9
Which of the following is part of the 12 practices defined in eXtreme Programming (XP)?

  • A. Risk management
  • B. Small releases
  • C. Project management
  • D. Project charter

Answer: B

NEW QUESTION 10
A “Scrum of Scrums” meeting is:

  • A. Another name for the daily standup project meeting in a Scrum team.
  • B. Amechanism that coordinates multiple teams working on a single project.
  • C. Aproject meeting that happens twice every day across the Scrum teams.
  • D. An occasional leadership meeting that provides direction to multiple Scrum teams.

Answer: B

NEW QUESTION 11
During iteration planning, the team is discussing the design for a user story. A team member states that a design document should be started since the system is complex in nature. Another team member responds that in Agile there is no documentation. How should the ScrumMaster respond?

  • A. Agree that documentation should be avoided, since it slows the progress of the team.
  • B. Explain that interactions are valued over documentation, but documentation is not forbidden.
  • C. Ask the manager if the technical processes mandate that designs be documented.
  • D. Ask the Product Owner if it is acceptable for the resources to spend time on documentation.

Answer: B

NEW QUESTION 12
The most powerful capability of Scrum teams is that they:

  • A. Work in timeboxed sprints.
  • B. Are self-organized and empowered.
  • C. Work from a prioritized backlog.
  • D. Value individuals and interactions.

Answer: B

NEW QUESTION 13
In reference to Scrum, each sprint should produce:

  • A. An increment of potentially shippable product functionality.
  • B. Aset of documented product requirements and specifications.
  • C. Arelease with testable and measurable functionality.
  • D. An increment of potentially testable product functionality.

Answer: A

NEW QUESTION 14
For a "caves and commonroom arrangement, the most appropriate prerequisite is that the people in the room must be working on:

  • A. Whatever they choose.
  • B. Individual projects.
  • C. The same set of multiple projects,
  • D. The same project.

Answer: D

NEW QUESTION 15
The following chart lists stories for a release of an Agile project:
PMI-ACP dumps exhibit
If the velocity of the team is 10, how many iterations will be needed to complete all of the stories?

  • A. 3
  • B. 4
  • C. 5
  • D. 7

Answer: B

NEW QUESTION 16
What is the first thing that a team should do to estimate user stories for a project?

  • A. Sort the user stories according to priority.
  • B. Schedule a team meeting to understand them.
  • C. Define the story points measure.
  • D. Estimate through function point analysis.

Answer: C

NEW QUESTION 17
......