NEW QUESTION 1
Which process involves identifying and documenting the logical relationships between project activities?

  • A. Develop Schedule
  • B. Sequence Activities
  • C. Create WBS
  • D. Applying leads and lags

Answer: B

NEW QUESTION 2
Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?

  • A. Initiating
  • B. Planning
  • C. Executing
  • D. Closing

Answer: C

NEW QUESTION 3
The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

  • A. Project Communications Management
  • B. Project Integration Management
  • C. Project Risk Management
  • D. Project Scope Management

Answer: B

NEW QUESTION 4
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:

  • A. Plan Schedule Management.
  • B. Develop Project Charter.
  • C. Develop Schedule.
  • D. Plan Scope Managemen

Answer: A

NEW QUESTION 5
An intentional activity to modify a nonconforming product or product component is called:

  • A. defect repair
  • B. work repair
  • C. corrective action
  • D. preventive action

Answer: A

NEW QUESTION 6
Which enterprise environmental factors may influence Plan Schedule Management?

  • A. Cultural views regarding time schedules and professional and ethical behaviors
  • B. Historical information and change control procedures
  • C. Risk control procedures and the probability and impact matrix
  • D. Resource availability and organizational culture and structure

Answer: D

NEW QUESTION 7
Which quality tool incorporates the upper and lower specification limits allowed within an agreement?

  • A. Control chart
  • B. Flowchart
  • C. Checksheet
  • D. Pareto diagram

Answer: A

NEW QUESTION 8
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

  • A. The risk of achieving the shortened project time is increased.
  • B. The critical path will have positive total float.
  • C. Contingency reserves are released for redeployment by the project manager.
  • D. Duration buffers are added to maintain a focus on planned activity duration

Answer: A

NEW QUESTION 9
A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:

  • A. To the project management plan.
  • B. To the risk register.
  • C. In the scope verification processes.
  • D. And their impact to the project in terms of time, cost, and ris

Answer: D

NEW QUESTION 10
The procurement process that documents agreements and related documentation for future reference is known as:

  • A. Plan Procurements.
  • B. Control Procurements.
  • C. Close Procurements.
  • D. Conduct Procurement

Answer: C

NEW QUESTION 11
An output of the Plan Quality Management process is:

  • A. A process improvement plan,
  • B. Quality control measurements.
  • C. Work performance information,
  • D. The project management plan.

Answer: A

NEW QUESTION 12
In the Plan Stakeholder Management process, expert judgment is used to:

  • A. Provide information needed to plan appropriate ways to engage project stakeholders.
  • B. Ensure comprehensive identification and listing of new stakeholders.
  • C. Analyze the information needed to develop the project scope statement.
  • D. Decide the level of engagement of the stakeholders at each required stag

Answer: D

NEW QUESTION 13
Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

  • A. Identify Risks
  • B. Plan Risk Management
  • C. Perform Qualitative Risk Analysis
  • D. Perform Quantitative Risk Analysis

Answer: C

NEW QUESTION 14
Sensitivity analysis is typically displayed as a/an:

  • A. Decision tree diagram.
  • B. Tornado diagram.
  • C. Pareto diagram.
  • D. Ishikawa diagra

Answer: B

NEW QUESTION 15
A project charter is an output of which Process Group?

  • A. Executing
  • B. Planning
  • C. Initiating
  • D. Closing

Answer: C

NEW QUESTION 16
What happens to a stakeholder's project influence over time?

  • A. Increases
  • B. Decreases
  • C. Stays the same
  • D. Has no bearing

Answer: B

NEW QUESTION 17
Which of the following includes how requirements activities will be planned, tracked, and reported?

  • A. Configuration management plan
  • B. Scope baseline
  • C. Requirements management plan
  • D. Schedule baseline

Answer: C

NEW QUESTION 18
Which cost estimate technique includes contingencies to account for cost uncertainty?

  • A. Vendor bid analysis
  • B. Three-point estimates
  • C. Parametric estimating
  • D. Reserve analysis

Answer: D