NEW QUESTION 1
Which process involves identifying and documenting the logical relationships between project activities?
- A. Develop Schedule
- B. Sequence Activities
- C. Create WBS
- D. Applying leads and lags
Answer: B
NEW QUESTION 2
Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?
- A. Initiating
- B. Planning
- C. Executing
- D. Closing
Answer: C
NEW QUESTION 3
The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?
- A. Project Communications Management
- B. Project Integration Management
- C. Project Risk Management
- D. Project Scope Management
Answer: B
NEW QUESTION 4
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:
- A. Plan Schedule Management.
- B. Develop Project Charter.
- C. Develop Schedule.
- D. Plan Scope Managemen
Answer: A
NEW QUESTION 5
An intentional activity to modify a nonconforming product or product component is called:
- A. defect repair
- B. work repair
- C. corrective action
- D. preventive action
Answer: A
NEW QUESTION 6
Which enterprise environmental factors may influence Plan Schedule Management?
- A. Cultural views regarding time schedules and professional and ethical behaviors
- B. Historical information and change control procedures
- C. Risk control procedures and the probability and impact matrix
- D. Resource availability and organizational culture and structure
Answer: D
NEW QUESTION 7
Which quality tool incorporates the upper and lower specification limits allowed within an agreement?
- A. Control chart
- B. Flowchart
- C. Checksheet
- D. Pareto diagram
Answer: A
NEW QUESTION 8
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
- A. The risk of achieving the shortened project time is increased.
- B. The critical path will have positive total float.
- C. Contingency reserves are released for redeployment by the project manager.
- D. Duration buffers are added to maintain a focus on planned activity duration
Answer: A
NEW QUESTION 9
A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:
- A. To the project management plan.
- B. To the risk register.
- C. In the scope verification processes.
- D. And their impact to the project in terms of time, cost, and ris
Answer: D
NEW QUESTION 10
The procurement process that documents agreements and related documentation for future reference is known as:
- A. Plan Procurements.
- B. Control Procurements.
- C. Close Procurements.
- D. Conduct Procurement
Answer: C
NEW QUESTION 11
An output of the Plan Quality Management process is:
- A. A process improvement plan,
- B. Quality control measurements.
- C. Work performance information,
- D. The project management plan.
Answer: A
NEW QUESTION 12
In the Plan Stakeholder Management process, expert judgment is used to:
- A. Provide information needed to plan appropriate ways to engage project stakeholders.
- B. Ensure comprehensive identification and listing of new stakeholders.
- C. Analyze the information needed to develop the project scope statement.
- D. Decide the level of engagement of the stakeholders at each required stag
Answer: D
NEW QUESTION 13
Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?
- A. Identify Risks
- B. Plan Risk Management
- C. Perform Qualitative Risk Analysis
- D. Perform Quantitative Risk Analysis
Answer: C
NEW QUESTION 14
Sensitivity analysis is typically displayed as a/an:
- A. Decision tree diagram.
- B. Tornado diagram.
- C. Pareto diagram.
- D. Ishikawa diagra
Answer: B
NEW QUESTION 15
A project charter is an output of which Process Group?
- A. Executing
- B. Planning
- C. Initiating
- D. Closing
Answer: C
NEW QUESTION 16
What happens to a stakeholder's project influence over time?
- A. Increases
- B. Decreases
- C. Stays the same
- D. Has no bearing
Answer: B
NEW QUESTION 17
Which of the following includes how requirements activities will be planned, tracked, and reported?
- A. Configuration management plan
- B. Scope baseline
- C. Requirements management plan
- D. Schedule baseline
Answer: C
NEW QUESTION 18
Which cost estimate technique includes contingencies to account for cost uncertainty?
- A. Vendor bid analysis
- B. Three-point estimates
- C. Parametric estimating
- D. Reserve analysis
Answer: D