NEW QUESTION 1
What does a CPI value greater than 1.0 indicate?
- A. Cost right at the estimated value
- B. Cost under the estimated value
- C. Cost right at the actual value
- D. Cost over the estimated value
Answer: B
NEW QUESTION 2
Which defines the portion of work included in a contract for items being purchased or acquired?
- A. Procurement management plan
- B. Evaluation criteria
- C. Work breakdown structure
- D. Procurement statement of work
Answer: D
NEW QUESTION 3
In which process might you use risk reassessment as a tool and technique?
- A. Qualitative risk analysis
- B. Risk monitoring and control
- C. Monitor and control project work
- D. Risk response planning
Answer: B
NEW QUESTION 4
Which of the following is an output of the Conduct Procurements process?
- A. Project statement of work
- B. Selected sellers
- C. Risk register updates
- D. Teaming agreements
Answer: B
NEW QUESTION 5
Which of the following is an example of push communication?
- A. Intranet sites
- B. Video conferencing
- C. Knowledge repositories
- D. Press releases
Answer: D
NEW QUESTION 6
The following is a network diagram for a project.
The free float for Activity E is how many days?
- A. 2
- B. 3
- C. 5
- D. 8
Answer: C
NEW QUESTION 7
The chart below is an example of a:
- A. Responsibility assignment matrix (RAM)
- B. Work breakdown structure (WBS)
- C. RACI chart
- D. Requirements traceability matrix
Answer: D
NEW QUESTION 8
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
- A. Three weeks
- B. Four weeks
- C. Five weeks
- D. Six weeks
Answer: C
NEW QUESTION 9
Which is a tool or technique used in Define Scope?
- A. Templates, forms, and standards
- B. Change requests
- C. Product analysis
- D. Project assumptions
Answer: C
NEW QUESTION 10
What are assigned risk ratings based upon?
- A. Root cause analysis
- B. Assessed probability and impact
- C. Expert judgment
- D. Risk Identification
Answer: B
NEW QUESTION 11
Which is an input to the Verify Scope process?
- A. Performance report
- B. Work breakdown structure (WBS)
- C. Requested changes
- D. Project management plan
Answer: D
NEW QUESTION 12
Resource calendars are included in the:
- A. staffing management plan.
- B. work breakdown structure (WBS).
- C. project communications plan.
- D. project charter.
Answer: A
NEW QUESTION 13
The creation of an internet site to engage stakeholders on a project is an example of which type of communication?
- A. Push
- B. Pull
- C. Interactive
- D. Iterative
Answer: B
NEW QUESTION 14
The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?
- A. Timing
- B. Methodology
- C. Risk categories
- D. Budgeting
Answer: A
NEW QUESTION 15
What is the name of the statistical method that helps identify which factors may influence
specific variables of a product or process under development or in production?
- A. Failure modes and effects analysis
- B. Design of experiments
- C. Quality checklist
- D. Risk analysis
Answer: B
NEW QUESTION 16
The three types of estimates that PERT uses to define an approximate range for an activity’s cost are:
- A. Parametric, most likely, and analogous.
- B. Least likely, analogous, and realistic.
- C. Parametric, optimistic, and pessimistic.
- D. Most likely, optimistic, and pessimistic.
Answer: D