NEW QUESTION 1
A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?

  • A. Slack
  • B. Float
  • C. Lag
  • D. Lead

Answer: C

NEW QUESTION 2
Which of the following is a schematic display of the project’s schedule activities and the logical relationships among them?

  • A. Gantt chart
  • B. Project schedule network diagram
  • C. Project milestone list
  • D. Activity list

Answer: B

NEW QUESTION 3
A required input for Create WBS is a project:

  • A. quality plan.
  • B. schedule network.
  • C. management document update.
  • D. scope statement.

Answer: D

NEW QUESTION 4
Which enterprise environmental factors are considered during cost estimating?

  • A. Marketplace conditions and commercial databases
  • B. Marketplace conditions and company structure
  • C. Commercial databases and company structure
  • D. Existing human resources and market place conditions

Answer: A

NEW QUESTION 5
The following chart contains information about the tasks in a project.
PMP dumps exhibit
Based on the chart, what is the cost variance (CV) for Task 6?

  • A. -2,000
  • B. 1,000
  • C. 2,000

Answer:

NEW QUESTION 6
The following chart contains information about the tasks in a project.
PMP dumps exhibit
Based on the chart, what is the schedule performance index (5PI) for Task 4?

  • A. 0.83
  • B. 0.9
  • C. 1.11
  • D. 1.33

Answer: C

NEW QUESTION 7
Plan-do-check-act is also known as:

  • A. prevention over inspection.
  • B. statistical sampling.
  • C. management responsibility,
  • D. continuous improvement.

Answer: D

NEW QUESTION 8
Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?

  • A. Cost Plus Award Fee Contract (CPAF)
  • B. Firm-Fixed -Price Contract (FFP)
  • C. Time and Material Contract (T&M)
  • D. Cost Plus Incentive Fee Contract (CPIF)

Answer: C

NEW QUESTION 9
Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?

  • A. Close Project or Phase
  • B. Conduct Procurements
  • C. Control Procurements
  • D. Close Procurements

Answer: D

NEW QUESTION 10
When sequencing activities, what does the common acronym FF stand for?

  • A. Fixed Fee
  • B. Free Float
  • C. Fixed Finish
  • D. Finish-to-Finish

Answer: D

NEW QUESTION 11
The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

  • A. management
  • B. response
  • C. tolerance
  • D. appetite

Answer: D

NEW QUESTION 12
A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:

  • A. triangular distribution
  • B. tornado diagram
  • C. beta distribution
  • D. fishbone diagram

Answer: B

NEW QUESTION 13
The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:

  • A. Validate Scope.
  • B. Plan Scope Management.
  • C. Control Scope.
  • D. Define Scope.

Answer: C

NEW QUESTION 14
Which of the following includes how requirements activities will be planned, tracked, and reported?

  • A. Configuration management plan
  • B. Scope baseline
  • C. Requirements management plan
  • D. Schedule baseline

Answer: C

NEW QUESTION 15
The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:

  • A. start-to-start (SS)
  • B. start-to-finish (SF)
  • C. finish-to-start (FS)
  • D. finish-to-finish (FF)

Answer: C

NEW QUESTION 16
Who is responsible for reviewing change requests and approving or rejecting the change requests?

  • A. Change control board
  • B. Project manager
  • C. Project management office
  • D. Project sponsor

Answer: B