NEW QUESTION 1

The following is a network diagram for a project.
PMP dumps exhibit
What is the critical path for the project?

  • A. A-B-C-F-G-I
  • B. A-B-C-F-H-I
  • C. A-D-E-F-G-I
  • D. A-D-E-F-H-I

Answer: A

NEW QUESTION 2

Administer Procurements is part of which Process Group?

  • A. Planning
  • B. Executing
  • C. Monitoring and Controlling
  • D. Closing

Answer: C

NEW QUESTION 3

Which of the following tools will be used to produce performance reports that provide information to stakeholders about project cost, schedule progress, and performance?

  • A. Communications methods
  • B. Reporting systems
  • C. Forecasting methods
  • D. Variance analysis

Answer: B

NEW QUESTION 4

The initial development of a Project Scope Management plan uses which technique?

  • A. Alternatives identification
  • B. Scope decomposition
  • C. Expert judgment
  • D. Product analysis

Answer: C

NEW QUESTION 5

Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?

  • A. Cost Plus Award Fee Contract (CPAF)
  • B. Firm-Fixed -Price Contract (FFP)
  • C. Time and Material Contract (T&M)
  • D. Cost Plus Incentive Fee Contract (CPIF)

Answer: C

NEW QUESTION 6

Outputs of the Control Communications process include:

  • A. expert judgment and change requests.
  • B. work performance information and change requests.
  • C. organizational process asset updates and an issue log.
  • D. project management plan updates and an issue log.

Answer: B

NEW QUESTION 7

The Perform Quality Assurance process occurs in which Process Group?

  • A. Executing
  • B. Monitoring and Controlling
  • C. Initiating
  • D. Planning

Answer: A

NEW QUESTION 8

Resource calendars are included in the:

  • A. staffing management plan.
  • B. work breakdown structure (WBS).
  • C. project communications plan.
  • D. project charter.

Answer: A

NEW QUESTION 9

Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:

  • A. quality audits
  • B. process analysis
  • C. statistical sampling
  • D. benchmarking

Answer: A

NEW QUESTION 10

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

  • A. 100
  • B. 120
  • C. 1,000
  • D. 1,200

Answer: A

NEW QUESTION 11

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

  • A. Perform Quality Assurance
  • B. Direct and Manage Project Work
  • C. Monitor and Control Project Work
  • D. Perform Integrated Change Control

Answer: D

NEW QUESTION 12

The chart below is an example of a:
PMP dumps exhibit

  • A. Responsibility assignment matrix (RAM)
  • B. Work breakdown structure (WBS)
  • C. RACI chart
  • D. Requirements traceability matrix

Answer: D

NEW QUESTION 13

Portfolio Management is management of:

  • A. a project by dividing the project into more manageable sub-projects.
  • B. a project by utilizing a portfolio of general management skills such as planning, organizing, staffing, executing, and controlling.
  • C. all projects undertaken by a company.
  • D. a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives.

Answer: D

NEW QUESTION 14

Which of the following will provide the basis for estimating, scheduling, executing, and monitoring and controlling project work?

  • A. Activities
  • B. Milestone list
  • C. Work breakdown structure (WBS)
  • D. Work packages

Answer: A

NEW QUESTION 15

In complex projects/ initiating processes should be completed:

  • A. Within a work package.
  • B. In each phase of the project.
  • C. To estimate schedule constraints.
  • D. To estimate resource allocations.

Answer: B

NEW QUESTION 16

Which project risk listed in the table below is most likely to occur?
PMP dumps exhibit

  • A. 1
  • B. 2
  • C. 3
  • D. 4

Answer: B

NEW QUESTION 17

Projects are undertaken by an organization to support the:

  • A. Product performance.
  • B. Budget process.
  • C. Collective capabilities.
  • D. Organizational strategy.

Answer: D

NEW QUESTION 18

The following is a network diagram for a project.
PMP dumps exhibit
What is the critical path for the project?

  • A. A-B-D-G
  • B. A-B-E-G
  • C. A-C-F-G
  • D. A-C-E-G

Answer: C

NEW QUESTION 19

The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:

  • A. Control Schedule.
  • B. Quality Control.
  • C. Perform Integrated Change Control.
  • D. Develop Schedule.

Answer: A

NEW QUESTION 20

Which type of analysis systemically gathers and analyzes qualitative and quantitative information to determine which interests should be taken into account throughout the project?

  • A. Product
  • B. Cost-benefit
  • C. Stakeholder
  • D. Research

Answer: C

NEW QUESTION 21
......