NEW QUESTION 1
The Human Resource Management processes are:

  • A. Develop Human Resource Plan, Acquire Project Team, Develop Project Team, and Manage Project Team.
  • B. Acquire Project Team, Manage Project Team, Manage Stakeholder Expectations, and Develop Project Team.
  • C. Acquire Project Team, Develop Human Resource Plan, Conflict Management, and Manage Project Team.
  • D. Develop Project Team, Manage Project Team, Estimate Activity Resources, and Acquire Project Team.

Answer: A

NEW QUESTION 2
Which of the following correctly lists the configuration management activities included in the
Integrated Change Control process?

  • A. Configuration definition, configuration status accounting, configuration monitoring and control
  • B. Configuration identification, configuration status accounting, configuration verification and audit
  • C. Configuration identification, configuration status reporting, configuration verification and audit
  • D. Configuration definition, configuration status reporting, configuration monitoring and Control

Answer: B

NEW QUESTION 3
Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?

  • A. Fixed Price with Economic Price Adjustments Contract (FP-EPA)
  • B. Cost-Reimbursable Contract (CR)
  • C. Firm-Fixed -Price Contract (FFP)
  • D. Fixed-Price-Incentive-Fee Contract (FPIF)

Answer: C

NEW QUESTION 4
The specific technique for identifying a problem, discovering the causes that lead to it, and developing preventive actions is:

  • A. Inspection
  • B. Use of quality checklists
  • C. Root cause analysis
  • D. Use of matrix diagrams

Answer: C

NEW QUESTION 5
The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

  • A. Work packages.
  • B. Accepted deliverables.
  • C. The WBS dictionary.
  • D. The scope baseline.

Answer: A

NEW QUESTION 6
Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?

  • A. Inspection
  • B. Quality audits
  • C. Design of experiments
  • D. Root cause analysis

Answer: D

NEW QUESTION 7
The cost of nonconformance in a project includes:

  • A. testing
  • B. rework
  • C. inspections
  • D. training

Answer: B

NEW QUESTION 8
The process of formalizing acceptance of the completed project deliverables is known as:

  • A. Validate Scope.
  • B. Close Project or Phase.
  • C. Control Quality.
  • D. Verify Scope.

Answer: A

NEW QUESTION 9
Project contracts generally fall into which of the following three broad categories?

  • A. Fixed-price, cost reimbursable, time and materials
  • B. Make-or-buy, margin analysis, fixed-price
  • C. Time and materials, fixed-price, margin analysis
  • D. Make-or-buy, lump-sum, cost-plus-incentive

Answer: A

NEW QUESTION 10
Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

  • A. Scope baseline
  • B. Scope management plan
  • C. Change management plan
  • D. Cost baseline

Answer: A

NEW QUESTION 11
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?

  • A. -8000
  • B. -2000
  • C. 2000
  • D. 8000

Answer: B

NEW QUESTION 12
An output of the Develop Project Team process is:

  • A. change requests
  • B. team performance assessments
  • C. project staff assignments
  • D. project documents updates

Answer: B

NEW QUESTION 13
Which of the following are documented directions to perform an activity that can reduce the probability of negative consequences associated with project risks?

  • A. Recommended corrective actions
  • B. Recommended preventive actions
  • C. Risk audits
  • D. Risk reassessments

Answer: B

NEW QUESTION 14
Who is responsible for determining which processes from the Process Groups will be employed and who will be performing them?

  • A. Project sponsor and project manager
  • B. Project sponsor and functional manager
  • C. Project manager and project team
  • D. Project team and functional manager

Answer: C

NEW QUESTION 15
Which of the following is an input to the Perform Qualitative Risk Analysis process?

  • A. Risk register
  • B. Risk data quality assessment
  • C. Risk categorization
  • D. Risk urgency

Answer: A

NEW QUESTION 16
Which statement is true about the project management body of knowledge?

  • A. Recognized by every project manager
  • B. Constantly evolving
  • C. The sum of all knowledge related to project management
  • D. A sum of knowledge that should be applied on every project

Answer: B