NEW QUESTION 1
Testing falls into which of the following categories of cost of quality?

  • A. Internal failure costs
  • B. Prevention costs
  • C. Appraisal costs
  • D. External failure costs

Answer: C

NEW QUESTION 2
As the project progresses, which of the following is routinely collected from the project activities?

  • A. Communication management activities
  • B. Change requests
  • C. Configuration verification and audit
  • D. Work performance information

Answer: D

NEW QUESTION 3
The following is a network diagram for a project.
PMP dumps exhibit
What is the critical path for the project?

  • A. A-B-C-F-G-I
  • B. A-B-C-F-H-I
  • C. A-D-E-F-G-I
  • D. A-D-E-F-H-I

Answer: A

NEW QUESTION 4
The run chart created during the Perform Quality Control process on a project is used to show the:

  • A. relationship between two variables
  • B. data points plotted in the order in which they occur
  • C. most common cause of problems in a process
  • D. frequency of occurrence

Answer: B

NEW QUESTION 5
Which type of chart is a graphic representation of a process showing the relationships among process steps?

  • A. Control
  • B. Bar
  • C. Flow
  • D. Pareto

Answer: C

NEW QUESTION 6
As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?

  • A. BAC
  • B. EAC
  • C. ETC
  • D. WBS

Answer: B

NEW QUESTION 7
Which of the following is a tool or technique of the Define Activities process?

  • A. Rolling wave planning
  • B. Precedence diagramming method (PDM)
  • C. Alternatives analysis
  • D. Parametric estimating

Answer: A

NEW QUESTION 8
The following is a network diagram for a project.
PMP dumps exhibit
The critical path for the project is how many days in duration?

  • A. 10
  • B. 12
  • C. 14
  • D. 17

Answer: D

NEW QUESTION 9
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

  • A. Negative
  • B. Zero
  • C. Positive
  • D. Free

Answer: C

NEW QUESTION 10
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

  • A. Finish-to-start planning
  • B. Rolling wave planning
  • C. Short term planning
  • D. Dependency determination

Answer: B

NEW QUESTION 11
Which of the following is an input into the Develop Project Team process?

  • A. Enterprise environmental factors
  • B. Organizational process assets
  • C. Project staff assignments
  • D. Performance reports

Answer: C

NEW QUESTION 12
Which of the following is the primary output of the Identify Risks process?

  • A. Risk management plan
  • B. Risk register
  • C. Change requests
  • D. Risk response plan

Answer: B

NEW QUESTION 13
In a project, total float measures the:

  • A. Ability to shuffle schedule activities to lessen the duration of the project.
  • B. Amount of time an activity can be extended or delayed without altering the project finish date.
  • C. Cost expended to restore order to the project schedule after crashing the schedule.
  • D. Estimate of the total resources needed for the project after performing a forward pass.

Answer: B

NEW QUESTION 14
The CPI is .92, and the EV is US$172,500. What is the actual cost of the project?

  • A. US$158,700
  • B. US$172,500
  • C. US$187,500
  • D. US$245,600

Answer: C

NEW QUESTION 15
Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?

  • A. Schedule network analysis
  • B. Reserve analysis
  • C. Alternative analysis
  • D. Variance analysis

Answer: D

NEW QUESTION 16
Which of the following is an example of a risk symptom?

  • A. Failure to meet intermediate milestones
  • B. Force of nature, such as a flood
  • C. Risk threshold target
  • D. Crashing, front loading, or fast tracking

Answer: A